THE CORRECT PROCEDURES FOR INSTALLING CAVITY WALL INSULATION.

Information provided by www.ukhomeinsulation.co.uk

--------------------------------------------------------------------------------
Method of Work

A cavity insulation Surveyor will inspect the properties to assess their suitability to receive insulation. The major points to be considered are:- Major cracks in the external walls. Defective pointing. Badly cracked or missing render. Signs of frost damage Any other defects that may lead to water penetration. If defects exist a summary of remedial work necessary to make the property suitable for insulating will be produced.
--------------------------------------------------------------------------------
Preparatory Work

After arrival on site, the Cavity wall Insulation Operative should check that:- All loose fittings (Ornaments, picture frames, ect.) have been removed from the external walls (provided access can be obtained). All doors and windows are in the closed position. The following work should be carried out where necessary to prevent the escape of material. Cavity brushes are fitted as required. Air bricks, if not adequately sleeved, should be lined to prevent blockage and to allow free flow of air.
--------------------------------------------------------------------------------
Preparatory Work

The blowing holes in the wall are approximately 25mm in diameter and are drilled at the intersection of the horizontal and vertical mortar joins so as to minimise damage to the brickwork (unless through rendered areas). Before starting the blowing process on any elevation, ALL holes must be drilled in that elevation. This is to ensure that no debris can fall onto the insulation material in the adjacent cavity and hence from a bridge between the inner and outer leaves. The drilling pattern is planned to include details such as openings, chimneys, flues and vents in accordance with the British Board of Agrément Certificate No 99/3637.
--------------------------------------------------------------------------------
Making Good

Mortar is mixed to match existing colour. Blow holes are repointed. Any loose material is swept up. The making good process can be carried out immediately after each blowing hole has been filled. This has been found to be the most effective method.
--------------------------------------------------------------------------------
Plant and Equipment

The following plant and equipment will be used on the project. Ladders. Ladder spreader bars (as required). 110v drills. Generators.Blowing Machine. Harnesses and Lanyards (as required). Under no circumstance is defective equipment to be used.
--------------------------------------------------------------------------------
First Aid

Although the materials used are relatively low risk, all operatives should be fully aware of emergency procedures.
--------------------------------------------------------------------------------
Personal Protective Equipment

Suitable personal protective equipment is provided to all operatives. Operatives should wear safety helmets on all sites, the only exception being :- For operatives working inside dwellings where there is no risk from falling objects. When inside site offices, canteens and sanitary conveniences. Safety footwear should be worn at all times. Ear protection should be worn whilst drilling or working in close proximity to generators. Gloves should be worn while handling insulation fibre and cement products. B.S.6016 Type 1 disposable face masks or other suitable HSE approved masks should be worn while handling insulation fibres, cement or while drilling mortar Eye protection should be worn whilst longer than 5m. The ladder should ideally be placed at about 75 degrees to the horizontal, i.e. 1m out from the building for every 4m in height. Ladders should be rested against a solid surface. It should not be placed against plastic against gutters or other such surfaces.
--------------------------------------------------------------------------------
Blowing Procedure.

The material is injected through a directional nozzle. Filling proceeds from the bottom to the top of the walls and from one end of the elevation to the other. As the blowing proceeds a record of the number of bags used is kept to confirm the installed density. If any hole excessive period a check should be made to ensure the material is not being blown into the floor spaces, lofts, ect.
--------------------------------------------------------------------------------
Final Check

Flues are checked to ensure they are clear (by a suitably trained gas engineer where required). Airbricks are checked to ensure they are clear. The amount of material used is recorded to ensure that a correct fill has been obtained.
--------------------------------------------------------------------------------
Remedial Works

Remedial works will be carried out by trained operatives using the appropriate methods and equipment.
--------------------------------------------------------------------------------

Visit www.ukhhomeinsulation.co.uk to get professionally installed, guaranteed loft insulation. You may be eligible for a grant and with that, it may cost less than DIY insulation.